Utah State University Life Sciences Building 

COMPLETED 2018 *

Location: Logan, Utah

Size: 103,000 sf.


  • Academic, clerical, and research spaces.

  • Laboratory variable air Volume single pass ventilation system with heat recovery.

  • Lab Air/Gas/Vac/Industrial Water and Acid Waste Neutralization System serve lab spaces.

  • Manifold exhaust Air Handling Unit located at the penthouse.

Gunnison Valley Hospital Addition

COMPLETED 2018*

Location: Gunnison, Utah

Addition Size: 10,600 sf

​

  • Addition of a new Pharmaceutical cleanroom, central sterile, and qty. 2 Operating rooms.

  • Enhancements to the existing hospital included renovated operating rooms and patient rooms.

Intermountain Healthcare LRH Cancer Center Addition

COMPLETED 2019 *

Location: Logan, Utah

Addition Size: 9,000 sf.


  • Amplification of the existing Logan Regional Hospital Cancer Center

  • New Chemo Compounding pharmaceutical cleanroom suit, 

  • Patient rooms and open/private infusion areas.

Utah State University Nutrition & Food Sciences Lab Controls Upgrade

COMPLETED 2019 *

Location: Logan, Utah


  • Renovation of existing research chemical laboratory mechanical ventilation systems.

  • Existing exhaust system upgraded to single-pass ventilation system with N+1 redundant high plume lab exhaust duplex fans.

  • All air controls were upgraded to venturi air control valves.

Utah State University Biology Building North Wing Renovation

COMPLETED 2021 *

Location: Logan, Utah


  • Complete renovation included new Mechanical and Plumbing systems to serve the N. Wing.

  • ​New teaching/chemical research laboratories, Animal research vivarium space, and Cadaver / anatomy teaching laboratory spaces.

  • Addition to the west wing for new entry lobby and basement mechanical room below. 

  • The new hydronic steam to water heat exchangers for whole building service.

  • New HVAC and plumbing systems to serve reconfigured spaces.

* Project designed & work completed as an employee of VBFA.

20150929_131413_edited_edited.jpg

Utility Distribution / Central Plant

Work: Projects

Utah State University Eastern Utility Master Plan 2016

COMPLETED 2016

Location: Price, Utah


  • 50 year phased build-out of campus Steam and Chilled water infrastructure.

  • Detailed analysis of existing systems allowed for proper recommendations for central boiler and chiller plant replacement.

  • Recommended tunnel extensions and required ventilation upgrades.

USUE Campus Library

USUE Campus Library

Central Boiler Plant

Central Boiler Plant

Tunnel Chilled Water

Tunnel Chilled Water

Tunnel Section

Tunnel Section

Utah State University Central Boiler Plant Renovation

COMPLETED 2018*

Location: Price, Utah

​

  • Extensive concrete lifting and new waste piping design greatly enhanced the building.

  • New condensate receiver/automatic pump-trap system replaced the existing equipment at below ground vault.

  • Ventilation and lighting added at the equipment vault location.

Central Boiler Plant

Central Boiler Plant

Waste Piping replacement

Waste Piping replacement

Old Condensate tank/pump/vent in Vault

Old Condensate tank/pump/vent in Vault

New Condensate Tank/pump/vent

New Condensate Tank/pump/vent

Utah State University Eastern Energy Metering and Steam Piping Replacement Projects

COMPLETED 2019*

Location: Price , Utah


  • Direct buried steam and condensate piping at the eastern quadrant of campus was replaced with an engineered piping system.

  • Metering was added to the Chilled water system at each building of campus to determine usage.

Direct Buried Steam/Condensate piping

Direct Buried Steam/Condensate piping

Steam/Condensate at Tunnel

Steam/Condensate at Tunnel

Utah State University Eastern Chiller Plant Renovation

2021

Location: Price, Utah


  • Replaced existing equipment with Qty. 3, 180 Ton Chillers for N+1 redundancy in campus cooling capacity.

  • Chilled water pumps replaced for new chilled water circulation. 

  • Campus chilled water plant system controls updated.

Existing Chiller Yard

Existing Chiller Yard

Chilled Water piping and pumps

Chilled Water piping and pumps

* Project designed & work completed as an employee of VBFA.

Pedestrian Path_edited.jpg

Municipal

Work: Projects

Salt Lake County - Mid-Valley Performing Arts Center

COMPLETED 2020*

Location: Taylorsville, Utah

Size: 70,000 sf.


  • Performance and rehearsal spaces.

  • 430-seat Maintstage Theater with Thermal Displacement Ventilation.

  • 220-seat Studio/Blackbox theater.

North Elevation MPAC

North Elevation MPAC

Pros. Theater Seating

Pros. Theater Seating

Mechanical Room

Mechanical Room

Studio Theater

Studio Theater

Air Handling Unit

Air Handling Unit

Cooling Tower

Cooling Tower

Below Seating Plenum Supply air distribution

Below Seating Plenum Supply air distribution